Special tribunal hears how some companies didn’t follow appointment process at Nkandla

The Special Investigating Unit wants to recoup R155 million from Minenhle Makhanya, the architect of Zuma’s controversial thatched roofed property which cost taxpayers in the region of R246 million. File picture: ANA

The Special Investigating Unit wants to recoup R155 million from Minenhle Makhanya, the architect of Zuma’s controversial thatched roofed property which cost taxpayers in the region of R246 million. File picture: ANA

Published Sep 29, 2021

Share

A key witness at the trial brought before the special tribunal by the Special Investigating Unit (SIU) in its bid to recoup R155 million from the architect of former president Jacob Zuma’s Nkandla homestead, has revealed how the appointments of some companies did not follow due process.

SIU wants to recoup R155m from Minenhle Makhanya, the architect of Zuma’s controversial thatched roofed property, which cost taxpayers in the region of R246m.

The witness, an investigator for the SIU, said some private professional teams were nominated and given direct appointments, and one was appointed as security consultant on an emergency basis and not reported to the Treasury up until the SIU investigations commenced.

Since Monday, when the trial commenced at the Pietermaritzburg High Court where it is being conducted in camera in order not to reveal various security details of Zuma and his family, the tribunal has heard shocking revelations of flouting of tender processes in the security upgrades at the Zuma home which eventually came to R246m.

The witness relayed how Moneymine Investments and Bonelena Construction and Projects (Pty) Ltd, two entities who did certain civil works purportedly undertaken at Nkandla, were appointed through a negotiated process and ultimately paid R54.8m.

The tribunal was told that Bonelena Construction and Projects (Pty) Ltd was paid millions for the outer perimeter fencing at Nkandla and that this payment was is allegedly made without the work being done while the witness also told the tribunal that in addition, Makhanya allegedly authorised the payment of "standing time" in amount of R82143.22 when this amount was not due and payable.

The witness told the tribunal that the amount of the claim is R13.6m and that in the claim of over designs of the scope of the works determined by SAPS and SANDF, it is contended that the total loss suffered by the Department of Public Works amount to R11.7m.

The witness said that on August 20, 2009 former minister of public works Geoff Doidge convened a meeting and suggested that the projects be synchronised and that the addition of the support staff, new residences, shaded parking, a helipad, air conditioning increased the budget and that the parking and other new items included hugely affected the costs.

She said the budget set for projects at the time set at R80.8m with R14.3m allocated to professional fees and disbursements and that a prepared report for further funding included R22m for the 2010/2011 financial year and R38.1m for 2012/2013 and when the memo was subsequently submitted an amount of R77m was made available with strict note that it be for security upgrades.

The witness said that almost a year later, on August 16 a further assessment was submitted and that the estimate did not have breakdown of the public and private job, adding that there was a difference of R88.5m with the previous work which was at R77m.

She said that included in the unit was the construction of a guard house, fire pool, car parking, and several housing units for workers, a clinic and a tuck shop with the total further increasing by R67m and a further R96.8m.

The witness added that later the amounts were revised and were then above R100m.

She went on to tell the court that as of January 25, 2010 the project cost was estimated at R161m and that there was no reasonable explanation for the basis for the division and estimates of the costs.

The witness also told the court that a mere three days later on January 28, 2010, the costs were revised at R216m and included costs of professional fees and that as of December 12, 2013 the costs were at R216m and there were no further claims.

Political Bureau